Hamer Warren Solar Farm

Hamer Warren Solar Farm is a 23 MW solar farm under construction in New Forest. Planning permission was granted on 3 February 2021, 4 months after submission. Operator of record: Somerley Estate.

23 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Somerley Estate
New Forest
Authority
England

Planning and build timeline

Application submitted1 October 2020
Permission granted3 February 2021
4 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

New Forest approves 75% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hamer Warren Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

New Forest’s record on solar

New Forest has decided 20 solar farms and approved 75%, taking a median of 2.2 months. See every solar farm decision in New Forest

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
100.4 km
Solar Photovoltaics · Operational
52.8 km
Solar Photovoltaics · Operational
20.45.7 km
Solar Photovoltaics · Operational
13.26.1 km
Solar Photovoltaics · Operational
137.1 km
Battery · Under Construction
49.97.9 km
Solar Photovoltaics · Operational
410.4 km
Solar Photovoltaics · Operational
3611 km

How big is Hamer Warren Solar Farm?

Hamer Warren Solar Farm has a recorded installed capacity of 23 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hamer Warren Solar Farm?

REPD records the operator as Somerley Estate. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hamer Warren Solar Farm approved and built?

The application was submitted on 1 October 2020. Permission was granted on 3 February 2021, 4 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8094.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode