Chapel Lane Parley Solar Farm Phase 3
Chapel Lane Parley Solar Farm Phase 3 is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 4 MW, and has been generating since 2015-09-01.
Planning and build timeline
| Application submitted | 2014-08-28 |
| Permission granted | 2015-01-30 5 months after submission |
| Operational | 2015-09-01 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Bournemouth, Christchurch and Poole
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bournemouth, Christchurch and Poole’s record on solar
Bournemouth, Christchurch and Poole has decided 25 solar farms and approved 88%, taking a median of 2.3 months. See every solar farm decision in Bournemouth, Christchurch and Poole →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chapel Lane Parley Solar Farm Phase 2 Solar Photovoltaics · Operational | 36 | 1 km |
Chapel Lane Parley Solar Farm Phase 1 Solar Photovoltaics · Operational | 20 | 1.3 km |
Chapel Lane ERF EfW Incineration · Under Construction | 3.4 | 1.7 km |
Eco Composting Biomass (dedicated) · Operational | 3.2 | 2 km |
Hale Farm Solar Photovoltaics · Operational | 8 | 2.8 km |
Woodtown Farm Solar Photovoltaics · Operational | 3.8 | 3 km |
Bedborough Farm Solar Photovoltaics · Operational | 7 | 4.5 km |
Homeland Solar Farm Solar Photovoltaics · Operational | 13.2 | 4.9 km |
How big is Chapel Lane Parley Solar Farm Phase 3?
Chapel Lane Parley Solar Farm Phase 3 has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chapel Lane Parley Solar Farm Phase 3?
REPD records the operator as Eco Sustainable Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chapel Lane Parley Solar Farm Phase 3 approved and built?
The application was submitted on 2014-08-28. Permission was granted on 2015-01-30, 5 months later. The site became operational on 2015-09-01, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2234.