Wednesbury is a 2 MW energy-from-waste plant under construction in Sandwell. Planning permission was granted on 25 March 2015, 3 months after submission. Operator of record: Kew Technologies (formerly JCB Broadcrown).

2 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
EfW Incineration
Technology
Kew Technologies (formerly JCB Broadcrown)
Sandwell
Authority
England

Planning and build timeline

Application submitted31 December 2014
Permission granted25 March 2015
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Sandwell: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wednesbury’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Battery · Operational
571.2 km
Advanced Conversion Technologies · Operational
404 km
Battery · Operational
24.1 km
Battery · Operational
44.1 km
Battery · Operational
414.4 km
Battery · Operational
49.94.9 km
Solar Photovoltaics · Operational
15.3 km
EfW Incineration · Under Construction
475.5 km

How big is Wednesbury?

Wednesbury has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wednesbury?

REPD records the operator as Kew Technologies (formerly JCB Broadcrown). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wednesbury approved and built?

The application was submitted on 31 December 2014. Permission was granted on 25 March 2015, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5030.