Hill of Tillymorgan (Kirkton Farm) Wind turbines
Hill of Tillymorgan (Kirkton Farm) Wind turbines is operational in Aberdeenshire with a recorded capacity of 9.6 MW, and has been generating since 2016-12-01.
Planning and build timeline
| Application submitted | 2011-03-16 |
| Permission granted | 2013-04-30 25 months after submission |
| Operational | 2016-12-01 43 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Overhill Farm, Rothienorman - Battery Energy Storage Battery · Under Construction | 49.9 | 8.5 km |
Glens of Foudland Wind Onshore · Operational | 26 | 9.2 km |
Castle of Auchry Farm Wind Onshore · Operational | 2.4 | 12 km |
Cairnmore Farm Wind Onshore · Operational | 2.6 | 12.7 km |
Dummuie Wind Onshore · Operational | 12.3 | 12.9 km |
Cairnmore Solar Park (extension) Solar Photovoltaics · Operational | 1.2 | 13.5 km |
Hill of Easterton Extension Wind Onshore · Operational | 2 | 13.5 km |
Hill of Easterton Wind Onshore · Operational | 2.5 | 13.5 km |
How big is Hill of Tillymorgan (Kirkton Farm) Wind turbines?
Hill of Tillymorgan (Kirkton Farm) Wind turbines has a recorded installed capacity of 9.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hill of Tillymorgan (Kirkton Farm) Wind turbines?
REPD records the operator as LocoGen/ Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hill of Tillymorgan (Kirkton Farm) Wind turbines approved and built?
The application was submitted on 2011-03-16. Permission was granted on 2013-04-30, 25 months later. The site became operational on 2016-12-01, 43 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3911.