Cairnmore Farm is operational in Aberdeenshire with a recorded capacity of 2.6 MW, and has been generating since 2010-07-10.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-07-10
Wind Onshore
Technology
Private Developer
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2008-04-18
Permission granted2009-10-27
18 months after submission
Operational2010-07-10
8 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Cairnmore Solar Park (extension)
Solar Photovoltaics · Operational
1.21 km
Cairnmore Solar Park
Solar Photovoltaics · Operational
3.81.1 km
Upper Wheedlemont Farm
Wind Onshore · Operational
1.73.8 km
Clashindarroch
Wind Onshore · Operational
376.5 km
Kildrummy Windfarm
Wind Onshore · Operational
18.412 km
Hill of Tillymorgan (Kirkton Farm) Wind turbines
Wind Onshore · Operational
9.612.7 km

How big is Cairnmore Farm?

Cairnmore Farm has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cairnmore Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cairnmore Farm approved and built?

The application was submitted on 2008-04-18. Permission was granted on 2009-10-27, 18 months later. The site became operational on 2010-07-10, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2724.