Novarly ParcelRenewable sites

Renewable sitesDummuie

Dummuie

Dummuie is an operational 12.3 MW onshore wind farm in Aberdeenshire, generating since 1 January 2007. Planning permission was granted on 20 February 2004, 6 months after submission. Operator of record: Tetro Energy Ltd (ECO2).

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2007
Wind Onshore
Technology
Tetro Energy Ltd (ECO2)
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted20 August 2003
Permission granted20 February 2004
6 months after submission
Operational1 January 2007
34 months after consent

Screening a site of your own?

RedlineUK · £39

Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dummuie’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
264.4 km
Wind Onshore · Operational
6.910.5 km
Battery · Under Construction
49.911.5 km
Wind Onshore · Operational
1012.5 km
Wind Onshore · Operational
12.512.6 km
Wind Onshore · Operational
9.612.9 km
Wind Onshore · Operational
3714.1 km
Wind Onshore · Operational
4.714.4 km

How big is Dummuie?

Dummuie has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dummuie?

REPD records the operator as Tetro Energy Ltd (ECO2). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dummuie approved and built?

The application was submitted on 20 August 2003. Permission was granted on 20 February 2004, 6 months later. The site became operational on 1 January 2007, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3200.

Novarly Parcel · official public data, read properly · parcel.novarly.com