Renewable sites › Glens of Foudland
Glens of Foudland
Glens of Foudland is operational in Aberdeenshire with a recorded capacity of 26 MW, and has been generating since 2005-07-22.
Planning and build timeline
| Application submitted | 2001-01-23 |
| Permission granted | 2001-10-04 8 months after submission |
| Operational | 2005-07-22 46 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dummuie Wind Onshore · Operational | 12.3 | 4.4 km |
Overhill Farm, Rothienorman - Battery Energy Storage Battery · Under Construction | 49.9 | 7.3 km |
Hill of Tillymorgan (Kirkton Farm) Wind turbines Wind Onshore · Operational | 9.6 | 9.2 km |
Shielburn Farm Wind Onshore · Operational | 6.9 | 10 km |
Gordonstown Hill Wind Farm Wind Onshore · Operational | 12.5 | 10.1 km |
How big is Glens of Foudland?
Glens of Foudland has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Glens of Foudland?
REPD records the operator as Green Investment Bank (Blackrock). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Glens of Foudland approved and built?
The application was submitted on 2001-01-23. Permission was granted on 2001-10-04, 8 months later. The site became operational on 2005-07-22, 46 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3311.
Novarly Parcel · official public data, read properly · parcel.novarly.com