Onshore wind planning in Westmorland and Furness

Westmorland and Furness has decided 17 onshore wind schemes and approved 35% of them, taking a median of 16.8 months to decide. Consented capacity: 42 MW. 1 application still awaiting a decision.

35%
Approved
6 granted · 11 refused
16.8 mo
Median decision
UK 11.5 mo
42 MW
Consented
172 MW refused
5
Appeals
2 allowed on appeal

How Westmorland and Furness compares

Against the 75 UK authorities with 5+ onshore wind decisions, Westmorland and Furness sits in the 8th percentile for approval rate (33 points below the England average) and the 28th percentile for speed.

Decisions by year

35Approved — 1 (2010)110Approved — 1 (2014)114Refused — 1 (2015)115Approved — 1 (2017)117Refused — 1 (2026)126
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (21)

SchemeMWStatusDecided
Greenhaume Farm, Askam Road - Wind Turbine
Solar Ventus Limited · B18/2024/0209 · 16.6 mo to decide
Application Refused2026-01-16
Greenhaume Farm, Askam Road - Wind Turbine
Solar Ventus Limited · B18/2024/0209
Application Submitted2024-08-28
Kirkby Moor
Npower Renewables · Unknown · 29.8 mo to decide
4.8Operational2017-06-13
Kirkby Moor Repowering
RWE Renewables · SL/2014/1220 · 8.9 mo to decide
18Application Refused2015-11-26
Hay Close Wind Farm
REG Windpower · 14/0637 · 3 mo to decide
10Appeal Withdrawn2014-10-16
Furness Wind Farm/High Winds (Harlock Repowering)
Baywind Co-op & Energy4All & Belltown Power · B06/2011/0662 · 34.6 mo to decide
11.5Operational2014-07-24
Killington Wind Farm
Banks Renewables · SL/2012/0845 · 16.4 mo to decide
10.2Abandoned2014-02-11
Armistead Wind Farm
Banks Renewables · SL/2008/0318 · 27.7 mo to decide
12Operational2010-07-15
Lamonby Wind Farm
Powergen /E.ON-UK · 05/0758
27Application Withdrawn2009-06-11
Grise
Wind Prospect Ireland Ltd. · 06/0075 · 36.2 mo to decide
27Appeal Refused2009-01-06
Berrier Hill
West Coast Energy · 07/0636 · 16.8 mo to decide
22.5Appeal Refused2009-01-02
Hoff Moor
Npower Renewables · 49.7 mo to decide
9Application Refused2007-02-22
Whinash Wind Farm
Renewable Development Company Ltd · 29.1 mo to decide
67.5Application Refused2006-03-02
Lowick Beacon
Ecotricity · 5/00/2278 · 7 mo to decide
4.2Application Refused2001-03-30
Lambrigg Wind Farm
Lambrigg Windfarm Ltd · 5/98/1478 · 12.3 mo to decide
6.5Operational1999-07-02
Barkin House Wind Farm
Farm Energy (The Wind Company Ltd) · 6.5 mo to decide
4.7Application Refused1999-04-07
Firbank Wind Farm
Colham Energy Ltd · 2.4 mo to decide
9.7Application Refused1998-12-08
Askam
Cannock Renewables · 30.8 mo to decide
4.6Operational1997-10-06
Lowick Beacon Windfarm
Micon Wind Turbines · 5951340 · 27.6 mo to decide
1.2Application Refused1997-10-06
Gunson Height Wind Farm
RWE npower · 21 mo to decide
7.8Application Refused1997-10-06
Harlock Hill Wind Farm
The Wind Company · 14.9 mo to decide
2.5Operational1996-05-03

Does Westmorland and Furness approve onshore wind schemes?

Yes — of the 17 onshore wind schemes Westmorland and Furness has decided, 35% were approved (6 granted, 11 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Westmorland and Furness?

The median time from application to decision is 16.8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Westmorland and Furness consented?

42 MW has been consented across 6 approved schemes, with 172 MW refused. A further 1 application awaits a decision.

Other technologies in Westmorland and Furness

Solar in Westmorland and FurnessBattery storage in Westmorland and Furness

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.