Novarly ParcelRenewable sites

Renewable sitesGranox Biogas Plant

Granox Biogas Plant

Granox Biogas Plant is operational in Halton with a recorded capacity of 5 MW, and has been generating since 2014-06-18.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-06-18
Anaerobic Digestion
Technology
ReFood UK
Halton
Authority
England

Planning and build timeline

Application submitted2012-03-21
Permission granted2012-10-19
7 months after submission
Operational2014-06-18
20 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant
Biomass (dedicated) · Operational
200.4 km
Leiria Way Car Park
Battery · Operational
1.6 km
Runcorn EfW
EfW Incineration · Operational
1003 km
Fiddlers Ferry Power Station - Battery storage
Battery · Under Construction
1504.5 km
Frodsham Marsh
Wind Onshore · Operational
50.46 km
Daresbury Science Park - Solar Array
Solar Photovoltaics · Operational
0.567.2 km
Arpley Landfill Scheme 'B'
Landfill Gas · Operational
7.97.2 km
Arpley Landfill Scheme 'A'
Landfill Gas · Operational
7.97.2 km

How big is Granox Biogas Plant?

Granox Biogas Plant has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Granox Biogas Plant?

REPD records the operator as ReFood UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Granox Biogas Plant approved and built?

The application was submitted on 2012-03-21. Permission was granted on 2012-10-19, 7 months later. The site became operational on 2014-06-18, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 306.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council