Fiddlers Ferry Power Station - Battery storage is under construction in Warrington with a recorded capacity of 150 MW.

150 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
SSE Enterprise (SSE PLC)
Warrington
Authority
England

Planning and build timeline

Application submitted2022-07-27
Permission granted2023-06-20
11 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Arpley Landfill Scheme 'A'
Landfill Gas · Operational
7.93 km
Arpley Landfill Scheme 'B'
Landfill Gas · Operational
7.93 km
Amazon Omega Business Park
Solar Photovoltaics · Operational
1.54.2 km
Daresbury Science Park - Solar Array
Solar Photovoltaics · Operational
0.564.5 km
Leiria Way Car Park
Battery · Operational
4.5 km
Granox Biogas Plant
Anaerobic Digestion · Operational
54.5 km
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant
Biomass (dedicated) · Operational
204.7 km
Former St Michaels Golf Course
Solar Photovoltaics · Under Construction
15.7 km

How big is Fiddlers Ferry Power Station - Battery storage?

Fiddlers Ferry Power Station - Battery storage has a recorded installed capacity of 150 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fiddlers Ferry Power Station - Battery storage?

REPD records the operator as SSE Enterprise (SSE PLC). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fiddlers Ferry Power Station - Battery storage approved and built?

The application was submitted on 2022-07-27. Permission was granted on 2023-06-20, 11 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9404.