Novarly ParcelRenewable sites

Renewable sitesArpley Landfill Scheme 'A'

Arpley Landfill Scheme 'A'

Arpley Landfill Scheme 'A' is operational in Warrington with a recorded capacity of 7.9 MW, and has been generating since 1999-12-10.

7.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1999-12-10
Landfill Gas
Technology
NOVERA
Warrington
Authority
England

Planning and build timeline

Application submitted1994-08-01
Permission granted1995-02-24
7 months after submission
Operational1999-12-10
57 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Arpley Landfill Scheme 'B'
Landfill Gas · Operational
7.90 km
Former St Michaels Golf Course
Solar Photovoltaics · Under Construction
12.9 km
Daresbury Science Park - Solar Array
Solar Photovoltaics · Operational
0.563 km
Fiddlers Ferry Power Station - Battery storage
Battery · Under Construction
1503 km
Warrington Home Solar Scheme
Solar Photovoltaics · Operational
5.33.2 km
Amazon Omega Business Park
Solar Photovoltaics · Operational
1.54 km
Leiria Way Car Park
Battery · Operational
6.7 km
Granox Biogas Plant
Anaerobic Digestion · Operational
57.2 km

How big is Arpley Landfill Scheme 'A'?

Arpley Landfill Scheme 'A' has a recorded installed capacity of 7.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arpley Landfill Scheme 'A'?

REPD records the operator as NOVERA. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arpley Landfill Scheme 'A' approved and built?

The application was submitted on 1994-08-01. Permission was granted on 1995-02-24, 7 months later. The site became operational on 1999-12-10, 57 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 547.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council