Renewable sites › Arpley Landfill Scheme 'B'
Arpley Landfill Scheme 'B'
Arpley Landfill Scheme 'B' is an operational 7.9 MW landfill gas site in Warrington, generating since 10 December 1999. Planning permission was granted on 14 July 1999, 3 months after submission. Operator of record: NOVERA.
Planning and build timeline
| Application submitted | 15 April 1999 |
| Permission granted | 14 July 1999 3 months after submission |
| Operational | 10 December 1999 5 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Warrington: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Arpley Landfill Scheme 'B'’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Green Belt — Warrington
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 7.9 | 0 km |
Solar Photovoltaics · Under Construction | 1 | 2.9 km |
Solar Photovoltaics · Operational | 0.56 | 3 km |
Battery · Under Construction | 150 | 3 km |
Solar Photovoltaics · Operational | 5.3 | 3.2 km |
Solar Photovoltaics · Operational | 1.5 | 4 km |
Battery · Operational | — | 6.7 km |
Anaerobic Digestion · Operational | 5 | 7.2 km |
How big is Arpley Landfill Scheme 'B'?
Arpley Landfill Scheme 'B' has a recorded installed capacity of 7.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Arpley Landfill Scheme 'B'?
REPD records the operator as NOVERA. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Arpley Landfill Scheme 'B' approved and built?
The application was submitted on 15 April 1999. Permission was granted on 14 July 1999, 3 months later. The site became operational on 10 December 1999, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 549.