Novarly ParcelRenewable sites

Renewable sitesGoonamarth Farm - Wind Turbine

Goonamarth Farm - Wind Turbine

Goonamarth Farm - Wind Turbine is under construction in Cornwall with a recorded capacity of 4.3 MW.

4.3 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Clean Earth Energy Limited
Cornwall
Authority
England

Planning and build timeline

Application submitted2024-01-26
Permission granted2024-05-01
3 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Manor Farm
Solar Photovoltaics · Operational
4.71.7 km
West Carclaze Solar Farm
Solar Photovoltaics · Operational
6.53 km
Ninnis Farm Solar
Solar Photovoltaics · Operational
53.5 km
Carloggas Farm Solar Park
Solar Photovoltaics · Operational
8.33.7 km
Land at Gilley's Mill Dam
Solar Photovoltaics · Operational
55.2 km
Cornwall ERC
EfW Incineration · Operational
205.3 km
Trethosa Farm Solar Park
Solar Photovoltaics · Operational
4.85.4 km
Eden Project Geothermal Energy Facility
Hot Dry Rocks (HDR) · Under Construction
75.4 km

How big is Goonamarth Farm - Wind Turbine?

Goonamarth Farm - Wind Turbine has a recorded installed capacity of 4.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Goonamarth Farm - Wind Turbine?

REPD records the operator as Clean Earth Energy Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Goonamarth Farm - Wind Turbine approved and built?

The application was submitted on 2024-01-26. Permission was granted on 2024-05-01, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 15275.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council