Novarly ParcelRenewable sites

Renewable sitesLand at Gilley's Mill Dam

Land at Gilley's Mill Dam

Land at Gilley's Mill Dam is operational in Cornwall with a recorded capacity of 5 MW, and has been generating since 2016-03-21.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-21
Solar Photovoltaics
Technology
NextEnergy Solar Fund
Cornwall
Authority
England

Planning and build timeline

Application submitted2011-05-18
Permission granted2011-08-05
3 months after submission
Operational2016-03-21
56 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Cornwall ERC
EfW Incineration · Operational
203.9 km
Woodlands Barton Wind Project
Wind Onshore · Operational
4.64.1 km
Woodlands Barton Solar Farm
Solar Photovoltaics · Operational
4.94.4 km
Bodwen Solar Park
Solar Photovoltaics · Operational
5.55.1 km
Goonamarth Farm - Wind Turbine
Wind Onshore · Under Construction
4.35.2 km
Carloggas Farm Solar Park
Solar Photovoltaics · Operational
8.35.2 km
West Carclaze Solar Farm
Solar Photovoltaics · Operational
6.55.5 km
Trethosa Farm Solar Park
Solar Photovoltaics · Operational
4.85.7 km

How big is Land at Gilley's Mill Dam?

Land at Gilley's Mill Dam has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Gilley's Mill Dam?

REPD records the operator as NextEnergy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Gilley's Mill Dam approved and built?

The application was submitted on 2011-05-18. Permission was granted on 2011-08-05, 3 months later. The site became operational on 2016-03-21, 56 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1815.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council