Renewable sites › Cornwall ERC
Cornwall ERC
Cornwall ERC is operational in Cornwall with a recorded capacity of 20 MW, and has been generating since 2017-04-04.
Planning and build timeline
| Application submitted | 2008-05-14 |
| Permission granted | 2011-05-19 36 months after submission |
| Operational | 2017-04-04 71 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Trethosa Farm Solar Park Solar Photovoltaics · Operational | 4.8 | 2 km |
KERNICK MICA DAM - SOLAR FARM Solar Photovoltaics · Operational | 12 | 2.4 km |
Carloggas Farm Solar Park Solar Photovoltaics · Operational | 8.3 | 2.5 km |
Land at Gilley's Mill Dam Solar Photovoltaics · Operational | 5 | 3.9 km |
Burthy Farm Solar Photovoltaics · Operational | 10 | 4.2 km |
Hewas Solar Farm Solar Photovoltaics · Operational | 5 | 4.5 km |
Trefullock Solar Farm Solar Photovoltaics · Operational | 5 | 4.8 km |
Land North East Of Penrose Far Solar Photovoltaics · Operational | 1.5 | 4.8 km |
How big is Cornwall ERC?
Cornwall ERC has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cornwall ERC?
REPD records the operator as SUEZ. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cornwall ERC approved and built?
The application was submitted on 2008-05-14. Permission was granted on 2011-05-19, 36 months later. The site became operational on 2017-04-04, 71 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 914.