Novarly ParcelRenewable sites

Renewable sitesTrethosa Farm Solar Park

Trethosa Farm Solar Park

Trethosa Farm Solar Park is operational in Cornwall with a recorded capacity of 4.8 MW, and has been generating since 2015-10-09.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-10-09
Solar Photovoltaics
Technology
Trethosa Solar Ltd
Cornwall
Authority
England

Planning and build timeline

Application submitted2014-01-28
Permission granted2014-06-06
4 months after submission
Operational2015-10-09
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
KERNICK MICA DAM - SOLAR FARM
Solar Photovoltaics · Operational
120.5 km
Carloggas Farm Solar Park
Solar Photovoltaics · Operational
8.31.7 km
Cornwall ERC
EfW Incineration · Operational
202 km
Hewas Solar Farm
Solar Photovoltaics · Operational
52.7 km
Burthy Farm
Solar Photovoltaics · Operational
103.4 km
Carnemough Farm Solar Park
Solar Photovoltaics · Operational
73.4 km
Trefullock Solar Farm
Solar Photovoltaics · Operational
54.3 km
Goonabarn Farm Wind Turbines
Wind Onshore · Operational
14.4 km

How big is Trethosa Farm Solar Park?

Trethosa Farm Solar Park has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trethosa Farm Solar Park?

REPD records the operator as Trethosa Solar Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trethosa Farm Solar Park approved and built?

The application was submitted on 2014-01-28. Permission was granted on 2014-06-06, 4 months later. The site became operational on 2015-10-09, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1896.