Ninnis Farm Solar is operational in Cornwall with a recorded capacity of 5 MW, and has been generating since 2013-03-30.
Planning and build timeline
| Application submitted | 2011-02-25 |
| Permission granted | 2011-06-03 3 months after submission |
| Operational | 2013-03-30 22 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on solar
Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Manor Farm Solar Photovoltaics · Operational | 4.7 | 1.9 km |
Goonamarth Farm - Wind Turbine Wind Onshore · Under Construction | 4.3 | 3.5 km |
Garlenick Estate 2 - Wind Turbines Wind Onshore · Operational | 4 | 3.8 km |
Carloggas Farm Solar Park Solar Photovoltaics · Operational | 8.3 | 4.5 km |
West Carclaze Solar Farm Solar Photovoltaics · Operational | 6.5 | 5.9 km |
Trethosa Farm Solar Park Solar Photovoltaics · Operational | 4.8 | 6 km |
KERNICK MICA DAM - SOLAR FARM Solar Photovoltaics · Operational | 12 | 6.2 km |
Carnemough Farm Solar Park Solar Photovoltaics · Operational | 7 | 6.8 km |
How big is Ninnis Farm Solar?
Ninnis Farm Solar has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ninnis Farm Solar?
REPD records the operator as The Green Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ninnis Farm Solar approved and built?
The application was submitted on 2011-02-25. Permission was granted on 2011-06-03, 3 months later. The site became operational on 2013-03-30, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1546.