Renewable sites › Tween Bridge Windfarm
Tween Bridge Windfarm
Tween Bridge Windfarm is an operational 44 MW onshore wind farm in Doncaster, generating since 27 February 2012. Planning permission was granted on 28 February 2008, 49 months after submission. Operator of record: E.ON Renewables.
Planning and build timeline
| Application submitted | 23 January 2004 |
| Permission granted | 28 February 2008 49 months after submission |
| Operational | 27 February 2012 48 months after consent |
Screening a site of your own?
Doncaster approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tween Bridge Windfarm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Doncaster’s record on onshore wind
Doncaster has decided 5 onshore wind schemes and approved 80%, taking a median of 49.2 months. See every onshore wind scheme decision in Doncaster →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 1.5 km |
Wind Onshore · Operational | 28.7 | 2.6 km |
Solar Photovoltaics · Operational | 0.27 | 4.4 km |
Solar Photovoltaics · Under Construction | 0.18 | 4.4 km |
Wind Onshore · Operational | 32.8 | 5.7 km |
Landfill Gas · Operational | 2.7 | 6.1 km |
Landfill Gas · Operational | 1.4 | 6.4 km |
Landfill Gas · Operational | 1.2 | 6.4 km |
How big is Tween Bridge Windfarm?
Tween Bridge Windfarm has a recorded installed capacity of 44 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tween Bridge Windfarm?
REPD records the operator as E.ON Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tween Bridge Windfarm approved and built?
The application was submitted on 23 January 2004. Permission was granted on 28 February 2008, 49 months later. The site became operational on 27 February 2012, 48 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3928.