Renewable sitesThorne Farm

Thorne Farm

Thorne Farm is operational in Doncaster with a recorded capacity of 5 MW, and has been generating since 2015-12-18.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-18
Solar Photovoltaics
Technology
Conergy
Doncaster
Authority
England

Planning and build timeline

Application submitted2014-09-12
Permission granted2015-04-16
7 months after submission
Operational2015-12-18
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Doncaster’s record on solar

Doncaster has decided 27 solar farms and approved 96%, taking a median of 2.3 months. See every solar farm decision in Doncaster

Other built sites within 15 km

SiteMWDistance
Tween Bridge Windfarm
Wind Onshore · Operational
441.5 km
Twin Rivers
Wind Onshore · Operational
28.73.6 km
Goole Fields
Wind Onshore · Operational
32.84.5 km
Goole Fields ll Wind Farm
Wind Onshore · Operational
34.95.5 km
Tudworth Field Road, Hatfield - Solar Panels
Solar Photovoltaics · Under Construction
0.185.8 km
Tudworth Field Road, Hatfield - Solar PV Panels
Solar Photovoltaics · Operational
0.275.8 km
Croda Chemicals Europe
Wind Onshore · Operational
37.1 km
Bootham Lane Landfill
Landfill Gas · Operational
2.77.2 km

How big is Thorne Farm?

Thorne Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thorne Farm?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thorne Farm approved and built?

The application was submitted on 2014-09-12. Permission was granted on 2015-04-16, 7 months later. The site became operational on 2015-12-18, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4857.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council