Novarly ParcelRenewable sites

Renewable sitesTurves Solar Farm

Turves Solar Farm

Turves Solar Farm is operational in Fenland with a recorded capacity of 5 MW, and has been generating since 2013-03-19.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-19
Solar Photovoltaics
Technology
Abbey Renewables
Fenland
Authority
England

Planning and build timeline

Application submitted2011-05-13
Permission granted2012-04-12
11 months after submission
Operational2013-03-19
11 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on solar

Fenland has decided 22 solar farms and approved 91%, taking a median of 2.8 months. See every solar farm decision in Fenland

Other built sites within 15 km

SiteMWDistance
Turves/Burtnhouse Solar Farm Extension
Solar Photovoltaics · Operational
4.70.1 km
Burnt House Farm
Wind Onshore · Operational
60.9 km
Greenvale AP Wind Turbine
Wind Onshore · Operational
1.51.8 km
Ranson Moor (phase 1)
Wind Onshore · Operational
64.4 km
Ranson Moor Wind Farm (Phase 2)
Wind Onshore · Operational
44.8 km
Glass Moor
Wind Onshore · Operational
165.8 km
Glass moor Extension
Wind Onshore · Operational
125.8 km
Boardinghouse Wind Farm
Wind Onshore · Operational
10.35.9 km

How big is Turves Solar Farm?

Turves Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Turves Solar Farm?

REPD records the operator as Abbey Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Turves Solar Farm approved and built?

The application was submitted on 2011-05-13. Permission was granted on 2012-04-12, 11 months later. The site became operational on 2013-03-19, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1171.

Novarly Parcel · official public data, read properly · parcel.novarly.com