Onshore wind planning in Fenland

Fenland has decided 20 onshore wind schemes and approved 85% of them, taking a median of 12.8 months to decide. Consented capacity: 133 MW. 1 application still awaiting a decision.

85%
Approved
17 granted · 3 refused
12.8 mo
Median decision
UK 11.5 mo
133 MW
Consented
38 MW refused
5
Appeals
3 allowed on appeal

How Fenland compares

Against the 75 UK authorities with 5+ onshore wind decisions, Fenland sits in the 85th percentile for approval rate (17 points above the England average) and the 57th percentile for speed.

Decisions by year

35Refused — 1 (2010)110Approved — 2 (2011)211Approved — 2 (2012)Refused — 2 (2012)412Approved — 1 (2023)123Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (24)

SchemeMWStatusDecided
Pondersbridge Farm, Oilmills Road - Wind Turbine
Whittome Farms · F/YR24/0986/F · 1.8 mo to decide
0.25Awaiting Construction2025-02-05
Pondersbridge Farm, Oilmills Road - Wind Turbine
Whittome Farms · F/YR23/0894/F · 1.8 mo to decide
Awaiting Construction2023-12-21
Delph Wind Farm
Wind Ventures · H14-0110-13
27Application Withdrawn2016-03-09
Greenvale AP Wind Turbine
Greenvale AP · F/YR12/0514/F · 2.5 mo to decide
1.5Operational2012-09-24
Treading Wind Farm - South Holland
Wind Ventures · H19-0081-11 · 19.3 mo to decide
5Application Refused2012-09-19
Treading Wind Farm - Fenland
Wind Ventures · F/YR11/0113/F · 17.4 mo to decide
15Appeal Refused2012-07-03
Glass moor Extension
EDF/China General Nuclear Power Corporation · F/YR11/0094/F · 14.3 mo to decide
12Operational2012-04-10
Greenvale AP Wind Turbine
Greenvale AP · F/YR11/0632/F · 5.1 mo to decide
2Revised2011-12-19
Burnt House Farm
Fivestone Ltd · F/YR09/0392/F · 24.9 mo to decide
6Operational2011-07-08
Boardinghouse Wind Farm
Ecogen · F/YR09/0562/F · 22.5 mo to decide
10.3Operational2011-07-06
Floods Ferry Farm
Private Developer · F/YR09/0272/F · 8.6 mo to decide
18Appeal Refused2010-01-04
MARCH SEWAGE TREATMENT WORKS - WIND TURBINE
TCI Renewables · F/YR07/0742/F · 19.2 mo to decide
2Operational2009-02-20
Whitemill Wind Farm
Co-operative Energy · F/YR07/1184/F · 12.8 mo to decide
14Operational2008-11-25
Stags Holt Extension
E.ON UK · F/YR07/0602/F · 16.1 mo to decide
2Operational2008-10-07
Whittlesey
REG Windpower (previously Cornwall Light and Power) · F/YR07/0413/F · 2.9 mo to decide
9Operational2007-07-09
Ranson Moor Wind Farm (Phase 2)
EcoGen Projects / Fenpower · F/YR06/0594/F · 9.2 mo to decide
4Operational2007-02-23
Honey Hill
Wind Prospect · F/99/0412/f
2Application Withdrawn2006-04-24
Darcey Lode
Wind Prospect · DARCEY LODE F/99/0411/F
2Application Withdrawn2005-11-01
Ranson Moor (phase 1)
Fenpower Limited · F/YR03/0990/F · 20.8 mo to decide
6Operational2005-04-25
Coldham
Wind Prospect / TXU · F/99/0410/F · 62.2 mo to decide
16Operational2004-10-07
Glass Moor
Fenland Windfarms Ltd · S/YR02/1327 · 6.1 mo to decide
16Operational2003-05-30
Long Hill Road
Snow Mountain Investment Ltd · S/YR01/1212/F · 21.1 mo to decide
2Operational2003-04-07
Coldham Hall
Co-op · F/YR02/0143/F · 9 mo to decide
14Operational2002-10-26
Stags Holt
Powergen / Wind Prospects · F/YR01/1269/F · 5 mo to decide
18Operational2002-05-23

Does Fenland approve onshore wind schemes?

Yes — of the 20 onshore wind schemes Fenland has decided, 85% were approved (17 granted, 3 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Fenland?

The median time from application to decision is 12.8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Fenland consented?

133 MW has been consented across 17 approved schemes, with 38 MW refused. A further 1 application awaits a decision.

Other technologies in Fenland

Solar in FenlandBattery storage in Fenland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.