Renewable sitesBurnt House Farm

Burnt House Farm

Burnt House Farm is an operational 6 MW onshore wind farm in Fenland, generating since 19 June 2013. Planning permission was granted on 8 July 2011, 25 months after submission. Operator of record: Fivestone Ltd.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 19 June 2013
Wind Onshore
Technology
Fivestone Ltd
Fenland
Authority
England

Planning and build timeline

Application submitted10 June 2009
Permission granted8 July 2011
25 months after submission
Operational19 June 2013
23 months after consent

Screening a site of your own?

RedlineUK · £39

Fenland approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Burnt House Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on onshore wind

Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.9 km
Solar Photovoltaics · Operational
4.71 km
Wind Onshore · Operational
1.52.7 km
Wind Onshore · Operational
65.2 km
Wind Onshore · Operational
165.5 km
Wind Onshore · Operational
125.5 km
Wind Onshore · Operational
45.7 km
Wind Onshore · Operational
10.36.4 km

How big is Burnt House Farm?

Burnt House Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burnt House Farm?

REPD records the operator as Fivestone Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burnt House Farm approved and built?

The application was submitted on 10 June 2009. Permission was granted on 8 July 2011, 25 months later. The site became operational on 19 June 2013, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3686.