Renewable sitesGipsy Lane

Gipsy Lane

Gipsy Lane is a 20 MW battery storage site under construction in Rochdale. Planning permission was granted on 16 March 2020, 4 months after submission. Operator of record: Arlington Energy.

20 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Arlington Energy
Rochdale
Authority
England

Planning and build timeline

Application submitted5 November 2019
Permission granted16 March 2020
4 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Rochdale approves 83% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Gipsy Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Rochdale’s record on battery storage

Rochdale has decided 6 battery storage schemes and approved 83%, taking a median of 4.9 months. See every battery storage scheme decision in Rochdale

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
400.1 km
Solar Photovoltaics · Under Construction
3.992.4 km
Landfill Gas · Operational
4.15.5 km
Liquid Air Energy Storage · Operational
56.5 km
Battery · Under Construction
577.3 km
Battery · Under Construction
207.5 km
Battery · Operational
207.7 km
Wind Onshore · Operational
13.69 km

How big is Gipsy Lane?

Gipsy Lane has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gipsy Lane?

REPD records the operator as Arlington Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gipsy Lane approved and built?

The application was submitted on 5 November 2019. Permission was granted on 16 March 2020, 4 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7632.