Novarly ParcelRenewable sites

Renewable sitesWhitegate Battery Storage

Whitegate Battery Storage

Whitegate Battery Storage is under construction in Oldham with a recorded capacity of 57 MW.

57 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Pelagic Energy (Constantine Energy)
Oldham
Authority
England

Planning and build timeline

Application submitted2022-02-14
Permission granted2022-05-19
3 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Oldham’s record on battery storage

Oldham has decided 5 battery storage schemes and approved 100%, taking a median of 3.1 months. See every battery storage scheme decision in Oldham

Other built sites within 15 km

SiteMWDistance
Chadderton - Battery energy storage facility
Battery · Under Construction
200.1 km
Land at Wrigley Head
Solar Photovoltaics · Under Construction
0.91.9 km
Reliance Street Mechanical Biological Treatment Facility (MBT)
Anaerobic Digestion · Operational
23.3 km
Moston Vale
Battery · Under Construction
104.1 km
Central Park - Solar photovaltics
Solar Photovoltaics · Operational
0.154.1 km
The National Cycling Centre - Solar Photovoltaic Panels
Solar Photovoltaics · Under Construction
0.925.5 km
The National Cycling Centre Velodrome
Solar Photovoltaics · Operational
0.75.5 km
City Football Academy, Ashton New Road - Solar panels
Solar Photovoltaics · Under Construction
3.385.9 km

How big is Whitegate Battery Storage?

Whitegate Battery Storage has a recorded installed capacity of 57 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whitegate Battery Storage?

REPD records the operator as Pelagic Energy (Constantine Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whitegate Battery Storage approved and built?

The application was submitted on 2022-02-14. Permission was granted on 2022-05-19, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10690.