Pilsworth Quarry Landfill Scheme

Pilsworth Quarry Landfill Scheme is operational in Bury with a recorded capacity of 4.1 MW, and has been generating since 1998-10-15.

4.1 MW
Capacity
as recorded in REPD
Operational
Status
since 1998-10-15
Landfill Gas
Technology
Terry Adams Ltd
Bury
Authority
England

Planning and build timeline

Application submitted1997-12-15
Permission granted1998-05-19
5 months after submission
Operational1998-10-15
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Pilsworth Landfill Site
Liquid Air Energy Storage · Operational
51.1 km
Lascar Works
Battery · Operational
202.9 km
Chamber House
Solar Photovoltaics · Under Construction
3.993.1 km
Astra Centre, Royal Barn Road - Energy Storage
Battery · Under Construction
405.4 km
Gipsy Lane
Battery · Under Construction
205.5 km
Clifton Hall
Landfill Gas · Operational
17.9 km
Whitegate Battery Storage
Battery · Under Construction
578.4 km
Chadderton - Battery energy storage facility
Battery · Under Construction
208.5 km

How big is Pilsworth Quarry Landfill Scheme?

Pilsworth Quarry Landfill Scheme has a recorded installed capacity of 4.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pilsworth Quarry Landfill Scheme?

REPD records the operator as Terry Adams Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pilsworth Quarry Landfill Scheme approved and built?

The application was submitted on 1997-12-15. Permission was granted on 1998-05-19, 5 months later. The site became operational on 1998-10-15, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 571.