Renewable sitesChadderton - Battery energy storage facility

Chadderton - Battery energy storage facility

Chadderton - Battery energy storage facility is a 20 MW battery storage site under construction in Oldham. Planning permission was granted on 9 December 2022, 8 months after submission. Operator of record: Field.

20 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Field
Oldham
Authority
England

Planning and build timeline

Application submitted8 April 2022
Permission granted9 December 2022
8 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Oldham approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Chadderton - Battery energy storage facility’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Oldham’s record on battery storage

Oldham has decided 5 battery storage schemes and approved 100%, taking a median of 3.1 months. See every battery storage scheme decision in Oldham

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
570.1 km
Solar Photovoltaics · Under Construction
0.91.8 km
Anaerobic Digestion · Operational
23.2 km
Battery · Under Construction
104 km
Solar Photovoltaics · Operational
0.154 km
Solar Photovoltaics · Under Construction
0.925.3 km
Solar Photovoltaics · Operational
0.75.4 km
Solar Photovoltaics · Under Construction
3.385.8 km

How big is Chadderton - Battery energy storage facility?

Chadderton - Battery energy storage facility has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chadderton - Battery energy storage facility?

REPD records the operator as Field. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chadderton - Battery energy storage facility approved and built?

The application was submitted on 8 April 2022. Permission was granted on 9 December 2022, 8 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11160.