Renewable sites › Long Meadow Farm
Long Meadow Farm
Long Meadow Farm is an operational 4.1 MW solar farm in Buckinghamshire, generating since 1 December 2015. Planning permission was granted on 10 January 2014, 4 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 4 September 2013 |
| Permission granted | 10 January 2014 4 months after submission |
| Operational | 1 December 2015 23 months after consent |
Screening a site of your own?
Buckinghamshire approves 90% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Long Meadow Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Buckinghamshire’s record on solar
Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 0.6 km |
Solar Photovoltaics · Operational | 6.2 | 3.1 km |
Solar Photovoltaics · Operational | 13.1 | 6.3 km |
Solar Photovoltaics · Operational | 5 | 6.4 km |
Anaerobic Digestion · Operational | 5 | 6.8 km |
Solar Photovoltaics · Operational | 24.2 | 7.1 km |
Solar Photovoltaics · Under Construction | 15 | 8.9 km |
Solar Photovoltaics · Operational | 5 | 9.2 km |
How big is Long Meadow Farm?
Long Meadow Farm has a recorded installed capacity of 4.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Long Meadow Farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Long Meadow Farm approved and built?
The application was submitted on 4 September 2013. Permission was granted on 10 January 2014, 4 months later. The site became operational on 1 December 2015, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1374.