Novarly ParcelRenewable sites

Renewable sitesGreat Seabrook Farm

Great Seabrook Farm

Great Seabrook Farm is operational in Buckinghamshire with a recorded capacity of 5 MW, and has been generating since 2015-09-28.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-09-28
Solar Photovoltaics
Technology
Conergy
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted2014-06-10
Permission granted2014-11-13
5 months after submission
Operational2015-09-28
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Buckinghamshire’s record on solar

Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire

Other built sites within 15 km

SiteMWDistance
Long Meadow Farm
Solar Photovoltaics · Operational
4.10.6 km
Church Farm
Solar Photovoltaics · Operational
6.22.6 km
Folly Farm
Solar Photovoltaics · Operational
13.16.4 km
Gib Lane Solar farm (Extension)
Solar Photovoltaics · Operational
56.6 km
Arla Dairy Site
Anaerobic Digestion · Operational
57 km
Gib Lane (Aston Clinton solar park)
Solar Photovoltaics · Operational
24.27.4 km
Trinity Hall Solar Farm
Solar Photovoltaics · Under Construction
158.4 km
Manor Farm
Solar Photovoltaics · Operational
58.7 km

How big is Great Seabrook Farm?

Great Seabrook Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Great Seabrook Farm?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Great Seabrook Farm approved and built?

The application was submitted on 2014-06-10. Permission was granted on 2014-11-13, 5 months later. The site became operational on 2015-09-28, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1842.

Novarly Parcel · official public data, read properly · parcel.novarly.com