Novarly ParcelRenewable sites

Renewable sitesClawdd Ddu PV

Clawdd Ddu PV

Clawdd Ddu PV is operational in Carmarthenshire with a recorded capacity of 13.5 MW, and has been generating since 2014-03-26.

13.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-26
Solar Photovoltaics
Technology
Elgin Energy EsCo
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted2013-03-27
Permission granted2013-10-07
6 months after submission
Operational2014-03-26
6 months after consent

Carmarthenshire’s record on solar

Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire

Other built sites within 15 km

SiteMWDistance
Pen Y Cae solar farm
Solar Photovoltaics · Operational
6.91.9 km
Saron Road solar park
Solar Photovoltaics · Operational
6.73 km
Pentre farm
Solar Photovoltaics · Operational
5.56 km
Pont Andrew Solar Farm
Solar Photovoltaics · Operational
1.56.9 km
Cefn Betingau Farm
Solar Photovoltaics · Operational
97 km
Mynydd Y Gwair Wind Farm
Wind Onshore · Operational
32.87.3 km
Mynydd y Betws
Wind Onshore · Operational
34.57.5 km
Gelliwern Isaf Farm
Solar Photovoltaics · Operational
68.5 km

How big is Clawdd Ddu PV?

Clawdd Ddu PV has a recorded installed capacity of 13.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clawdd Ddu PV?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clawdd Ddu PV approved and built?

The application was submitted on 2013-03-27. Permission was granted on 2013-10-07, 6 months later. The site became operational on 2014-03-26, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1951.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council