Renewable sites › Former St Michaels Golf Course
Former St Michaels Golf Course
Former St Michaels Golf Course is under construction in Warrington with a recorded capacity of 1 MW.
Planning and build timeline
| Application submitted | 2018-02-23 |
| Permission granted | 2018-04-27 2 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Warrington
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Warrington’s record on solar
Warrington has decided 27 solar farms and approved 81%, taking a median of 1.8 months. See every solar farm decision in Warrington →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Daresbury Science Park - Solar Array Solar Photovoltaics · Operational | 0.56 | 2.9 km |
Arpley Landfill Scheme 'B' Landfill Gas · Operational | 7.9 | 2.9 km |
Arpley Landfill Scheme 'A' Landfill Gas · Operational | 7.9 | 2.9 km |
Warrington Home Solar Scheme Solar Photovoltaics · Operational | 5.3 | 3 km |
Fiddlers Ferry Power Station - Battery storage Battery · Under Construction | 150 | 5.7 km |
Amazon Omega Business Park Solar Photovoltaics · Operational | 1.5 | 6.3 km |
Leiria Way Car Park Battery · Operational | — | 8.7 km |
Butchersfield Landfill Site Landfill Gas · Operational | 3 | 9 km |
How big is Former St Michaels Golf Course?
Former St Michaels Golf Course has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Former St Michaels Golf Course?
REPD records the operator as Halton Borough Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Former St Michaels Golf Course approved and built?
The application was submitted on 2018-02-23. Permission was granted on 2018-04-27, 2 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6560.