Novarly ParcelRenewable sites

Renewable sitesAmazon Omega Business Park

Amazon Omega Business Park

Amazon Omega Business Park is operational in Warrington with a recorded capacity of 1.5 MW, and has been generating since 2020-01-01.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-01-01
Solar Photovoltaics
Technology
Amazon UK Services / Push Energy
Warrington
Authority
England

Planning and build timeline

Application submitted2019-02-20
Permission granted2019-04-30
2 months after submission
Operational2020-01-01
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Warrington’s record on solar

Warrington has decided 27 solar farms and approved 81%, taking a median of 1.8 months. See every solar farm decision in Warrington

Other built sites within 15 km

SiteMWDistance
Arpley Landfill Scheme 'B'
Landfill Gas · Operational
7.94 km
Arpley Landfill Scheme 'A'
Landfill Gas · Operational
7.94 km
Fiddlers Ferry Power Station - Battery storage
Battery · Under Construction
1504.2 km
Warrington Home Solar Scheme
Solar Photovoltaics · Operational
5.34.3 km
Former St Michaels Golf Course
Solar Photovoltaics · Under Construction
16.3 km
Daresbury Science Park - Solar Array
Solar Photovoltaics · Operational
0.567 km
Granox Biogas Plant
Anaerobic Digestion · Operational
58.4 km
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant
Biomass (dedicated) · Operational
208.4 km

How big is Amazon Omega Business Park?

Amazon Omega Business Park has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Amazon Omega Business Park?

REPD records the operator as Amazon UK Services / Push Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Amazon Omega Business Park approved and built?

The application was submitted on 2019-02-20. Permission was granted on 2019-04-30, 2 months later. The site became operational on 2020-01-01, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7248.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council