Butchersfield Landfill Site is an operational 3 MW landfill gas site in Warrington, generating since 16 October 1995. Planning permission was granted on 5 September 1995, 4 months after submission. Operator of record: NORWEB Generation Limited.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 16 October 1995
Landfill Gas
Technology
NORWEB Generation Limited
Warrington
Authority
England

Planning and build timeline

Application submitted28 April 1995
Permission granted5 September 1995
4 months after submission
Operational16 October 1995
1 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Warrington: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Butchersfield Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.14.4 km
Landfill Gas · Operational
24.6 km
Landfill Gas · Operational
5.94.6 km
Biomass (dedicated) · Operational
41.65.3 km
Solar Photovoltaics · Operational
5.38 km
Solar Photovoltaics · Under Construction
19 km
Solar Photovoltaics · Under Construction
0.59.2 km
Landfill Gas · Operational
5.310.7 km

How big is Butchersfield Landfill Site?

Butchersfield Landfill Site has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Butchersfield Landfill Site?

REPD records the operator as NORWEB Generation Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Butchersfield Landfill Site approved and built?

The application was submitted on 28 April 1995. Permission was granted on 5 September 1995, 4 months later. The site became operational on 16 October 1995, 1 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 577.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode