Arlesey Landfill Site
Arlesey Landfill Site is an operational 1.1 MW landfill gas site in Central Bedfordshire, generating since 18 July 1998. Planning permission was granted on 11 April 1994, 2 months after submission. Operator of record: Waste Recycling Group.
Planning and build timeline
| Application submitted | 15 February 1994 |
| Permission granted | 11 April 1994 2 months after submission |
| Operational | 18 July 1998 51 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Central Bedfordshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Arlesey Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 2.3 | 0.5 km |
Landfill Gas · Operational | 1.5 | 3.1 km |
Solar Photovoltaics · Operational | 13 | 4.6 km |
Wind Onshore · Operational | 20 | 6.7 km |
Anaerobic Digestion · Operational | 2.3 | 9.2 km |
Solar Photovoltaics · Operational | 1 | 11.5 km |
Solar Photovoltaics · Operational | 10 | 14.2 km |
Battery · Operational | 6 | 14.2 km |
How big is Arlesey Landfill Site?
Arlesey Landfill Site has a recorded installed capacity of 1.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Arlesey Landfill Site?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Arlesey Landfill Site approved and built?
The application was submitted on 15 February 1994. Permission was granted on 11 April 1994, 2 months later. The site became operational on 18 July 1998, 51 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 664.