Renewable sites › Land North of Chiltern Greeen
Land North of Chiltern Greeen
Land North of Chiltern Greeen is operational in Central Bedfordshire with a recorded capacity of 5 MW, and has been generating since 2016-03-10.
Planning and build timeline
| Application submitted | 2015-03-27 |
| Permission granted | 2015-06-26 3 months after submission |
| Operational | 2016-03-10 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Central Bedfordshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Central Bedfordshire’s record on solar
Central Bedfordshire has decided 32 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Central Bedfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ld At Lawrence End Park &, Dane Street Solar Photovoltaics · Operational | 5 | 1.4 km |
Caddington Solar Farm (Phase 1) Solar Photovoltaics · Operational | 3 | 7.7 km |
Caddington Solar Farm (Phase 2) Solar Photovoltaics · Operational | 5 | 8.1 km |
Flamingo House Solar Photovoltaics · Operational | 1 | 10.6 km |
Computacenter Warehouse Solar Photovoltaics · Under Construction | 2 | 12.2 km |
Chapel Farm Battery · Operational | 49.5 | 12.4 km |
Iron Mountain Site Solar Photovoltaics · Operational | 0.3 | 12.5 km |
Sundon Substation Battery · Operational | 49.9 | 12.7 km |
How big is Land North of Chiltern Greeen?
Land North of Chiltern Greeen has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land North of Chiltern Greeen?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land North of Chiltern Greeen approved and built?
The application was submitted on 2015-03-27. Permission was granted on 2015-06-26, 3 months later. The site became operational on 2016-03-10, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5162.