Renewable sites › Ferrymuir
Ferrymuir
Ferrymuir is under construction in Fife with a recorded capacity of 49.9 MW.
Planning and build timeline
| Application submitted | 2019-09-23 |
| Permission granted | 2020-01-10 4 months after submission |
| Operational | not recorded |
Fife’s record on battery storage
Fife has decided 23 battery storage schemes and approved 96%, taking a median of 3.9 months. See every battery storage scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Cupar Wastewater Treatment Works Solar Farm Solar Photovoltaics · Operational | 0.62 | 3.4 km |
Lower Melville Wood Landfill Gas · Operational | 1 | 5.9 km |
Sustainable Power and Research Campus Biomass (dedicated) · Operational | 6.5 | 11.1 km |
Eden Campus Solar Photovoltaics · Operational | 1 | 11.2 km |
Banbeath Industrial Estate Solar Array Solar Photovoltaics · Under Construction | 4.19 | 12.4 km |
Wormit Solar Farm Solar Photovoltaics · Operational | 4 | 12.7 km |
Diageo Biomass Energy Project Biomass (dedicated) · Operational | 5.5 | 13.5 km |
Markinch Biomass CHP Plant Biomass (dedicated) · Operational | 65 | 14.3 km |
How big is Ferrymuir?
Ferrymuir has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ferrymuir?
REPD records the operator as Gore Street Energy Storage Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ferrymuir approved and built?
The application was submitted on 2019-09-23. Permission was granted on 2020-01-10, 4 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7371.
Novarly Parcel · official public data, read properly · parcel.novarly.com