Novarly ParcelRenewable sites

Renewable sitesCupar Wastewater Treatment Works Solar Farm

Cupar Wastewater Treatment Works Solar Farm

Cupar Wastewater Treatment Works Solar Farm is an operational 0.62 MW solar farm in Fife, generating since 19 July 2021. Planning permission was granted on 19 January 2021, 3 months after submission. Operator of record: Scottish Water (Dundee).

0.62 MW
Capacity
as recorded in REPD
Operational
Status
since 19 July 2021
Solar Photovoltaics
Technology
Scottish Water (Dundee)
Fife
Authority
Scotland

Planning and build timeline

Application submitted23 October 2020
Permission granted19 January 2021
3 months after submission
Operational19 July 2021
6 months after consent

Screening a site of your own?

RedlineUK · £39

Fife approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cupar Wastewater Treatment Works Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fife’s record on solar

Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
49.93.4 km
Biomass (dedicated) · Operational
6.57.8 km
Solar Photovoltaics · Operational
17.9 km
Landfill Gas · Operational
19.3 km
Solar Photovoltaics · Operational
410.5 km
Solar Photovoltaics · Under Construction
4.1913.9 km
Solar Photovoltaics · Under Construction
14.9 km

How big is Cupar Wastewater Treatment Works Solar Farm?

Cupar Wastewater Treatment Works Solar Farm has a recorded installed capacity of 0.62 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cupar Wastewater Treatment Works Solar Farm?

REPD records the operator as Scottish Water (Dundee). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cupar Wastewater Treatment Works Solar Farm approved and built?

The application was submitted on 23 October 2020. Permission was granted on 19 January 2021, 3 months later. The site became operational on 19 July 2021, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8205.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode