Diageo Biomass Energy Project

Diageo Biomass Energy Project is an operational 5.5 MW biomass plant in Fife, generating since 8 May 2013. Planning permission was granted on 4 November 2008, 7 months after submission. Operator of record: Diageo.

5.5 MW
Capacity
as recorded in REPD
Operational
Status
since 8 May 2013
Biomass (dedicated)
Technology
Diageo
Fife
Authority
Scotland

Planning and build timeline

Application submitted11 April 2008
Permission granted4 November 2008
7 months after submission
Operational8 May 2013
54 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Fife: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Diageo Biomass Energy Project’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
4.192.1 km
Wind Onshore · Operational
18.42.4 km
Hydrogen · Under Construction
2.6 km
Solar Photovoltaics · Operational
56.5 km
Biomass (dedicated) · Operational
656.7 km
Wind Offshore · Operational
76.9 km
Wind Onshore · Operational
1.56.9 km
Wind Onshore · Operational
1.57 km

How big is Diageo Biomass Energy Project?

Diageo Biomass Energy Project has a recorded installed capacity of 5.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Diageo Biomass Energy Project?

REPD records the operator as Diageo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Diageo Biomass Energy Project approved and built?

The application was submitted on 11 April 2008. Permission was granted on 4 November 2008, 7 months later. The site became operational on 8 May 2013, 54 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 172.