Novarly ParcelRenewable sites

Renewable sitesEsholt WWTW

Esholt WWTW

Esholt WWTW is operational in Bradford with a recorded capacity of 3 MW, and has been generating since 2014-10-03.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-10-03
Sewage Sludge Digestion
Technology
Yorkshire Water
Bradford
Authority
England

Planning and build timeline

Application submitted2011-09-30
Permission granted2012-03-30
6 months after submission
Operational2014-10-03
30 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Morrisons, Bradford Road, Idle - Solar PV Panels
Solar Photovoltaics · Operational
0.82.7 km
Trafalgar House Police Station - Installation Of Solar PV System
Solar Photovoltaics · Under Construction
7 km
Bradford West Substation (Harrop Edge Farm)
Battery · Under Construction
49.910.7 km
Buslingthorpe Power Station (Leeds North)
Biomass (dedicated) · Operational
211.7 km
Regent Street, Sheepscar - Solar Panels
Solar Photovoltaics · Operational
0.2212.7 km
TF and JH Braime Holdings Factory
Solar Photovoltaics · Operational
0.213.4 km
Holmfield - Battery Energy Storage
Battery · Under Construction
0.2514 km
LVF Packaging - Solar Panel
Solar Photovoltaics · Operational
0.314.1 km

How big is Esholt WWTW?

Esholt WWTW has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Esholt WWTW?

REPD records the operator as Yorkshire Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Esholt WWTW approved and built?

The application was submitted on 2011-09-30. Permission was granted on 2012-03-30, 6 months later. The site became operational on 2014-10-03, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4695.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council