Holmfield - Battery Energy Storage

Holmfield - Battery Energy Storage is under construction in Bradford with a recorded capacity of 0.25 MW.

0.25 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Parkinson Spencer Refractories
Bradford
Authority
England

Planning and build timeline

Application submitted2022-07-22
Permission granted2023-03-10
8 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bradford’s record on battery storage

Bradford has decided 8 battery storage schemes and approved 88%, taking a median of 5.2 months. See every battery storage scheme decision in Bradford

Other built sites within 15 km

SiteMWDistance
Ovenden Moor (Repower)
Wind Onshore · Operational
185 km
Bradford West Substation (Harrop Edge Farm)
Battery · Under Construction
49.95.6 km
Trafalgar House Police Station - Installation Of Solar PV System
Solar Photovoltaics · Under Construction
8.2 km
Morrisons, Bradford Road, Idle - Solar PV Panels
Solar Photovoltaics · Operational
0.811.5 km
United Anodisers, Red Doles Lane - Solar Panels
Solar Photovoltaics · Under Construction
0.3112.7 km
Vine Street EfW
EfW Incineration · Operational
9.512.8 km
Esholt WWTW
Sewage Sludge Digestion · Operational
314 km

How big is Holmfield - Battery Energy Storage?

Holmfield - Battery Energy Storage has a recorded installed capacity of 0.25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Holmfield - Battery Energy Storage?

REPD records the operator as Parkinson Spencer Refractories. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Holmfield - Battery Energy Storage approved and built?

The application was submitted on 2022-07-22. Permission was granted on 2023-03-10, 8 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11674.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council