Renewable sites › Holmfield - Battery Energy Storage
Holmfield - Battery Energy Storage
Holmfield - Battery Energy Storage is a 0.25 MW battery storage site under construction in Bradford. Planning permission was granted on 10 March 2023, 8 months after submission. Operator of record: Parkinson Spencer Refractories.
Planning and build timeline
| Application submitted | 22 July 2022 |
| Permission granted | 10 March 2023 8 months after submission |
| Operational | not recorded |
Screening a site of your own?
Bradford approves 88% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Holmfield - Battery Energy Storage’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Bradford
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bradford’s record on battery storage
Bradford has decided 8 battery storage schemes and approved 88%, taking a median of 5.2 months. See every battery storage scheme decision in Bradford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 18 | 5 km |
Battery · Under Construction | 49.9 | 5.6 km |
Solar Photovoltaics · Under Construction | — | 8.2 km |
Solar Photovoltaics · Operational | 0.8 | 11.5 km |
Solar Photovoltaics · Under Construction | 0.31 | 12.7 km |
EfW Incineration · Operational | 9.5 | 12.8 km |
Sewage Sludge Digestion · Operational | 3 | 14 km |
How big is Holmfield - Battery Energy Storage?
Holmfield - Battery Energy Storage has a recorded installed capacity of 0.25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Holmfield - Battery Energy Storage?
REPD records the operator as Parkinson Spencer Refractories. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Holmfield - Battery Energy Storage approved and built?
The application was submitted on 22 July 2022. Permission was granted on 10 March 2023, 8 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11674.