Renewable sites › Marston Solar Farm
Marston Solar Farm
Marston Solar Farm is operational in South Kesteven with a recorded capacity of 4.9 MW, and has been generating since 2011-07-18.
Planning and build timeline
| Application submitted | 2011-03-29 |
| Permission granted | 2011-05-19 2 months after submission |
| Operational | 2011-07-18 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Kesteven’s record on solar
South Kesteven has decided 28 solar farms and approved 86%, taking a median of 3.1 months. See every solar farm decision in South Kesteven →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Grantham Solar Farm Solar Photovoltaics · Operational | 5 | 2.1 km |
Copley Farm Solar Photovoltaics · Operational | 30 | 6.6 km |
Lodge Farm - Orston Solar Photovoltaics · Operational | 12.4 | 9.5 km |
Grange Solar Farm Solar Photovoltaics · Operational | 4.6 | 10.6 km |
Elton solar farm Solar Photovoltaics · Operational | 5 | 10.8 km |
High Dyke (Mill Farm) Solar Photovoltaics · Operational | 5 | 11.4 km |
Balderton Biomass (dedicated) · Operational | 20.3 | 11.9 km |
Hawton Wind Farm Wind Onshore · Operational | 9 | 12.1 km |
How big is Marston Solar Farm?
Marston Solar Farm has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Marston Solar Farm?
REPD records the operator as Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Marston Solar Farm approved and built?
The application was submitted on 2011-03-29. Permission was granted on 2011-05-19, 2 months later. The site became operational on 2011-07-18, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1433.
Novarly Parcel · official public data, read properly · parcel.novarly.com