Novarly ParcelRenewable sites

Renewable sitesChapel Lane Parley Solar Farm Phase 1

Chapel Lane Parley Solar Farm Phase 1

Chapel Lane Parley Solar Farm Phase 1 is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 20 MW, and has been generating since 2014-03-31.

20 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
Solar Power Generation Limited
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted2012-11-28
Permission granted2013-03-28
4 months after submission
Operational2014-03-31
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bournemouth, Christchurch and Poole’s record on solar

Bournemouth, Christchurch and Poole has decided 25 solar farms and approved 88%, taking a median of 2.3 months. See every solar farm decision in Bournemouth, Christchurch and Poole

Other built sites within 15 km

SiteMWDistance
Chapel Lane Parley Solar Farm Phase 2
Solar Photovoltaics · Operational
360.6 km
Chapel Lane ERF
EfW Incineration · Under Construction
3.40.6 km
Eco Composting
Biomass (dedicated) · Operational
3.20.7 km
Chapel Lane Parley Solar Farm Phase 3
Solar Photovoltaics · Operational
41.3 km
Hale Farm
Solar Photovoltaics · Operational
81.5 km
Woodtown Farm
Solar Photovoltaics · Operational
3.81.9 km
Bedborough Farm
Solar Photovoltaics · Operational
75.3 km
Homeland Solar Farm
Solar Photovoltaics · Operational
13.26.2 km

How big is Chapel Lane Parley Solar Farm Phase 1?

Chapel Lane Parley Solar Farm Phase 1 has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chapel Lane Parley Solar Farm Phase 1?

REPD records the operator as Solar Power Generation Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chapel Lane Parley Solar Farm Phase 1 approved and built?

The application was submitted on 2012-11-28. Permission was granted on 2013-03-28, 4 months later. The site became operational on 2014-03-31, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2282.

Novarly Parcel · official public data, read properly · parcel.novarly.com