Clashindarroch
Clashindarroch is an operational 37 MW onshore wind farm in Aberdeenshire, generating since 26 June 2015. Planning permission was granted on 14 December 2010, 18 months after submission. Operator of record: Vattenfall.
Planning and build timeline
| Application submitted | 1 June 2009 |
| Permission granted | 14 December 2010 18 months after submission |
| Operational | 26 June 2015 54 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Clashindarroch’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 1.7 | 4.8 km |
Wind Onshore · Operational | 2.6 | 6.5 km |
Solar Photovoltaics · Operational | 3.8 | 6.9 km |
Solar Photovoltaics · Operational | 1.2 | 7 km |
Wind Onshore · Operational | 10 | 11 km |
Wind Onshore · Operational | 12.3 | 14.1 km |
How big is Clashindarroch?
Clashindarroch has a recorded installed capacity of 37 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clashindarroch?
REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clashindarroch approved and built?
The application was submitted on 1 June 2009. Permission was granted on 14 December 2010, 18 months later. The site became operational on 26 June 2015, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4623.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode