Cairnborrow
Cairnborrow is operational in Aberdeenshire with a recorded capacity of 10 MW, and has been generating since 2017-02-09.
Planning and build timeline
| Application submitted | 2013-10-09 |
| Permission granted | 2014-08-25 11 months after submission |
| Operational | 2017-02-09 30 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Edintore Wind Farm Wind Onshore · Operational | 18 | 6 km |
Blackhillock Electricity Substation - Battery Energy Storage System Battery · Under Construction | 300 | 6.7 km |
Clashindarroch Wind Onshore · Operational | 37 | 11 km |
Dummuie Wind Onshore · Operational | 12.3 | 12.5 km |
Glenfiddich Distillery Anaerobic Digestion · Operational | 1.5 | 13.5 km |
Garbet Windfarm - Wind Farm & Storage facility Battery · Under Construction | 3 | 14 km |
Garbet Windfarm - Wind Farm & Storage facility Wind Onshore · Under Construction | 46.2 | 14 km |
How big is Cairnborrow?
Cairnborrow has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cairnborrow?
REPD records the operator as Engie (GDF Suez). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cairnborrow approved and built?
The application was submitted on 2013-10-09. Permission was granted on 2014-08-25, 11 months later. The site became operational on 2017-02-09, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4350.