Cairnborrow

Cairnborrow is operational in Aberdeenshire with a recorded capacity of 10 MW, and has been generating since 2017-02-09.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-02-09
Wind Onshore
Technology
Engie (GDF Suez)
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2013-10-09
Permission granted2014-08-25
11 months after submission
Operational2017-02-09
30 months after consent

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Edintore Wind Farm
Wind Onshore · Operational
186 km
Blackhillock Electricity Substation - Battery Energy Storage System
Battery · Under Construction
3006.7 km
Clashindarroch
Wind Onshore · Operational
3711 km
Dummuie
Wind Onshore · Operational
12.312.5 km
Glenfiddich Distillery
Anaerobic Digestion · Operational
1.513.5 km
Garbet Windfarm - Wind Farm & Storage facility
Battery · Under Construction
314 km
Garbet Windfarm - Wind Farm & Storage facility
Wind Onshore · Under Construction
46.214 km

How big is Cairnborrow?

Cairnborrow has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cairnborrow?

REPD records the operator as Engie (GDF Suez). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cairnborrow approved and built?

The application was submitted on 2013-10-09. Permission was granted on 2014-08-25, 11 months later. The site became operational on 2017-02-09, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4350.