Renewable sites › Duke Of Gloucester Barracks
Duke Of Gloucester Barracks
Duke Of Gloucester Barracks is operational in Cotswold with a recorded capacity of 1.4 MW, and has been generating since 2021-09-01.
Planning and build timeline
| Application submitted | 2019-11-26 |
| Permission granted | 2020-05-04 5 months after submission |
| Operational | 2021-09-01 16 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cotswold’s record on solar
Cotswold has decided 18 solar farms and approved 100%, taking a median of 3.8 months. See every solar farm decision in Cotswold →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Siddington Solar Farm Solar Photovoltaics · Under Construction | 19.94 | 2.2 km |
Cirencester Solar Farm Solar Photovoltaics · Operational | 23 | 2.5 km |
Cirencester Solar Farm Battery · Operational | 10 | 2.5 km |
Crucis Park Solar Photovoltaics · Operational | 12.5 | 4 km |
Chelworth Industrial Estate Solar Park Solar Photovoltaics · Operational | 1 | 7.1 km |
Kemble Wick Solar Photovoltaics · Operational | 49.9 | 8.2 km |
Water Eaton Farm / Port Farm Solar Photovoltaics · Operational | 34.8 | 8.7 km |
Bentham Farm Solar Photovoltaics · Operational | 8 | 9.3 km |
How big is Duke Of Gloucester Barracks?
Duke Of Gloucester Barracks has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Duke Of Gloucester Barracks?
REPD records the operator as Ministry of Defence. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Duke Of Gloucester Barracks approved and built?
The application was submitted on 2019-11-26. Permission was granted on 2020-05-04, 5 months later. The site became operational on 2021-09-01, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7599.