Novarly ParcelRenewable sites

Renewable sitesDuke Of Gloucester Barracks

Duke Of Gloucester Barracks

Duke Of Gloucester Barracks is an operational 1.4 MW solar farm in Cotswold, generating since 1 September 2021. Planning permission was granted on 4 May 2020, 5 months after submission. Operator of record: Ministry of Defence.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2021
Solar Photovoltaics
Technology
Ministry of Defence
Cotswold
Authority
England

Planning and build timeline

Application submitted26 November 2019
Permission granted4 May 2020
5 months after submission
Operational1 September 2021
16 months after consent

Screening a site of your own?

RedlineUK · £39

Cotswold approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Duke Of Gloucester Barracks’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cotswold’s record on solar

Cotswold has decided 18 solar farms and approved 100%, taking a median of 3.8 months. See every solar farm decision in Cotswold

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
19.942.2 km
Battery · Operational
102.5 km
Solar Photovoltaics · Operational
232.5 km
Solar Photovoltaics · Operational
12.54 km
Solar Photovoltaics · Operational
17.1 km
Solar Photovoltaics · Operational
49.98.2 km
Solar Photovoltaics · Operational
34.88.7 km
Solar Photovoltaics · Operational
89.3 km

How big is Duke Of Gloucester Barracks?

Duke Of Gloucester Barracks has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Duke Of Gloucester Barracks?

REPD records the operator as Ministry of Defence. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Duke Of Gloucester Barracks approved and built?

The application was submitted on 26 November 2019. Permission was granted on 4 May 2020, 5 months later. The site became operational on 1 September 2021, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7599.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode