Renewable planning SolarCotswold

Solar planning in Cotswold

Cotswold has decided 18 solar farms and approved 100% of them, taking a median of 3.8 months to decide. Consented capacity: 140 MW. 1 application still awaiting a decision.

100%
Approved
18 granted · 0 refused
3.8 mo
Median decision
UK 2.3 mo
140 MW
Consented
across approved schemes
2
Appeals
2 allowed on appeal

How Cotswold compares

Against the 298 UK authorities with 5+ solar decisions, Cotswold sits in the 77th percentile for approval rate (7 points above the England average) and the 17th percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 4 (2013)413Approved — 1 (2015)115Approved — 1 (2016)116Approved — 1 (2020)120Approved — 1 (2021)121Approved — 2 (2022)222Approved — 2 (2023)223Approved — 4 (2024)424Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (21)

SchemeMWStatusDecided
Westonbirt School - Solar Panels
Westonbirt School · 25/02620/FUL
Application Withdrawn2025-11-27
Guiting Manor Farms, Guiting Power - Solar Panels
Guiting Manor Farms Limited · 25/02050/SPANOT · 1.4 mo to decide
0.28Awaiting Construction2025-08-14
Spratsgate Lane, Siddington - Solar Farm and Battery Energy Storage System
Aura Power Developments Limited · 25/01623/FUL
25Application Submitted2025-06-12
Welsh Way - Solar PV Farm
Innova Renewables · 23/03907/FUL · 9.4 mo to decide
13Awaiting Construction2024-09-23
Cotswold Leisure Centre, Old Tetbury Road - Solar Panels
Cotswold Leisure · 24/01915/SPANOT · 2.4 mo to decide
0.3Awaiting Construction2024-09-12
Peters Farm, Middle Hill - Solar Panels
A D Brain & Son · 24/01496/SPANOT · 1.2 mo to decide
0.15Awaiting Construction2024-06-28
Cotswold District Council, Trinity Road - Solar panels
Cotswold District Council · 23/03929/SPANOT · 1 mo to decide
0.16Awaiting Construction2024-01-16
Cotswold School, Station Road - Solar Panels
Solar Options for Schools Limited · 23/02865/FUL · 1.8 mo to decide
0.3Awaiting Construction2023-11-29
Hangmans Hall Farm, Broad Campden - Solar Panels
Northwick Estate Partnership · 23/01069/SPANOT · 1.7 mo to decide
0.2Awaiting Construction2023-05-26
Tetbury Audi, Quercus Road - Solar Array
Tetbury Audi · 22/03260/SPANOT · 1.7 mo to decide
0.2Awaiting Construction2022-11-04
Kemble Wick
Aura Power · PL/2021/06919 · 7.9 mo to decide
49.9Operational2022-03-25
Siddington Solar Farm
Gresham House / Anesco Limited · 20/04499/FUL · 4.9 mo to decide
19.94Under Construction2021-05-21
Duke Of Gloucester Barracks
Ministry of Defence · 19/04344/FUL · 5.3 mo to decide
1.4Operational2020-05-04
Broadfield Farmhouse
British Solar Renewables · 15/03186/FUL · 4.8 mo to decide
5Planning Permission Expired2016-02-24
Cirencester Solar Farm
Warrington Borough Council / Statkraft · 15/01923/FUL · 4.3 mo to decide
23Operational2015-09-17
Crucis Park
Solar Planning Limited · 13/03656/FUL · 3.9 mo to decide
12.5Operational2013-12-20
Norton Hall
Ms Power Projects Ltd · 12/05095/FUL · 10.8 mo to decide
2.8Operational2013-10-10
LAND AT SANDPOOL FARM
Wiltshire Wildlife Trust and Bath and West Community Energy Ltd · 13/00276/FUL
1Application Withdrawn2013-06-26
The Rainbows Solar Farm
Innogy (previously BELECTRIC Solar) · 13/00578/FUL · 4 mo to decide
4Operational2013-06-13
Northwick Estate (Extension)
Northwick Power Ltd · 12/05072/FUL · 3.7 mo to decide
2.2Operational2013-03-05
Springhill Solar Park (Northwick)
Greencoat Capital · 11/01247/FUL · 3.1 mo to decide
5Operational2011-07-21

Does Cotswold approve solar farms?

Yes — of the 18 solar farms Cotswold has decided, 100% were approved (18 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Cotswold?

The median time from application to decision is 3.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Cotswold consented?

140 MW has been consented across 18 approved schemes. A further 1 application awaits a decision.

Other technologies in Cotswold

Battery storage in CotswoldOnshore wind in Cotswold

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.