Novarly ParcelRenewable sites

Renewable sitesKemble Wick

Kemble Wick

Kemble Wick is operational in Cotswold with a recorded capacity of 49.9 MW, and has been generating since 2026-02-01.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2026-02-01
Solar Photovoltaics
Technology
Aura Power
Cotswold
Authority
England

Planning and build timeline

Application submitted2021-07-27
Permission granted2022-03-25
8 months after submission
Operational2026-02-01
46 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cotswold’s record on solar

Cotswold has decided 18 solar farms and approved 100%, taking a median of 3.8 months. See every solar farm decision in Cotswold

Other built sites within 15 km

SiteMWDistance
Lodge Farm (Poulshot)
Solar Photovoltaics · Operational
14.55 km
Minety South 2 - Battery Storage Facility
Battery · Operational
49.996.3 km
Siddington Solar Farm
Solar Photovoltaics · Under Construction
19.946.3 km
Stonehill Energy Storage / Upper Minety
Battery · Operational
506.4 km
Stonehill Energy Storage / Upper Minety
Battery · Operational
506.4 km
Stonehill Energy Storage / Lower Minety
Battery · Operational
506.4 km
Marsh Farm
Solar Photovoltaics · Operational
146.7 km
Malmesbury Solar
Solar Photovoltaics · Operational
56.8 km

How big is Kemble Wick?

Kemble Wick has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kemble Wick?

REPD records the operator as Aura Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kemble Wick approved and built?

The application was submitted on 2021-07-27. Permission was granted on 2022-03-25, 8 months later. The site became operational on 2026-02-01, 46 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8136.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council