Renewable sites › Greendykeside
Greendykeside
Greendykeside is an operational 4 MW onshore wind farm in North Lanarkshire, generating since 1 November 2007. Planning permission was granted on 11 May 2005, 8 months after submission. Operator of record: A7 Energy.
Planning and build timeline
| Application submitted | 13 September 2004 |
| Permission granted | 11 May 2005 8 months after submission |
| Operational | 1 November 2007 30 months after consent |
Screening a site of your own?
North Lanarkshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Greendykeside’s recorded coordinate — swap in your own postcode or coordinates.
North Lanarkshire’s record on onshore wind
North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 24 | 1.3 km |
Landfill Gas · Operational | 4 | 2.7 km |
Landfill Gas · Operational | 2 | 2.7 km |
Landfill Gas · Operational | 1.9 | 2.7 km |
Landfill Gas · Operational | 2.2 | 2.7 km |
Landfill Gas · Operational | 2 | 2.7 km |
Landfill Gas · Operational | 2.2 | 2.7 km |
Wind Onshore · Operational | 2.5 | 6.7 km |
How big is Greendykeside?
Greendykeside has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Greendykeside?
REPD records the operator as A7 Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Greendykeside approved and built?
The application was submitted on 13 September 2004. Permission was granted on 11 May 2005, 8 months later. The site became operational on 1 November 2007, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3236.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode