Renewable sites › Drayton Manor Farm
Drayton Manor Farm
Drayton Manor Farm is operational in Stratford-on-Avon with a recorded capacity of 25 MW, and has been generating since 2016-03-23.
Planning and build timeline
| Application submitted | 2015-01-30 |
| Permission granted | 2015-06-08 4 months after submission |
| Operational | 2016-03-23 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stratford-on-Avon’s record on solar
Stratford-on-Avon has decided 36 solar farms and approved 94%, taking a median of 3.7 months. See every solar farm decision in Stratford-on-Avon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burton Farm Solar Photovoltaics · Operational | 4.4 | 3 km |
Alscot Biomass (dedicated) · Operational | 1.6 | 7.1 km |
Littleton Solar Farm Solar Photovoltaics · Operational | 30 | 10.8 km |
Littleton Solar Farm Battery · Operational | — | 10.8 km |
Crimscote Solar Farm and Storage Project Solar Photovoltaics · Under Construction | 49.99 | 10.9 km |
Crimscote Solar Farm and Storage Project Battery · Under Construction | — | 10.9 km |
Norton Hall Solar Photovoltaics · Operational | 2.8 | 11.1 km |
Salford Lodge Solar Photovoltaics · Operational | 5 | 11.7 km |
How big is Drayton Manor Farm?
Drayton Manor Farm has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Drayton Manor Farm?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Drayton Manor Farm approved and built?
The application was submitted on 2015-01-30. Permission was granted on 2015-06-08, 4 months later. The site became operational on 2016-03-23, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5020.