Novarly ParcelRenewable sites

Renewable sitesLittleton Solar Farm

Littleton Solar Farm

Littleton Solar Farm is operational in Wychavon, and has been generating since 2026-03-27.

Capacity
as recorded in REPD
Operational
Status
since 2026-03-27
Battery
Technology
Stark Energy / SSE Renewables
Wychavon
Authority
England

Planning and build timeline

Application submitted2020-09-09
Permission granted2021-01-06
4 months after submission
Operational2026-03-27
63 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wychavon’s record on battery storage

Wychavon has decided 12 battery storage schemes and approved 100%, taking a median of 5.7 months. See every battery storage scheme decision in Wychavon

Other built sites within 15 km

SiteMWDistance
Littleton Solar Farm
Solar Photovoltaics · Operational
300 km
Plant Produce - Solar PV panels
Solar Photovoltaics · Operational
0.153.8 km
Sytchwythy Fields
Solar Photovoltaics · Operational
1.44.6 km
Norton Hall
Solar Photovoltaics · Operational
2.84.7 km
Bypass Nurseries Solar Farm
Solar Photovoltaics · Operational
3.34.9 km
The Rainbows Solar Farm
Solar Photovoltaics · Operational
45.1 km
Mount Farm
Solar Photovoltaics · Operational
226.3 km
Willersey solar farm
Battery · Operational
16.8 km

How big is Littleton Solar Farm?

REPD does not record an installed capacity for Littleton Solar Farm.

Who operates Littleton Solar Farm?

REPD records the operator as Stark Energy / SSE Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Littleton Solar Farm approved and built?

The application was submitted on 2020-09-09. Permission was granted on 2021-01-06, 4 months later. The site became operational on 2026-03-27, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9039.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council