Novarly ParcelRenewable sites

Renewable sitesLathom (Pilkington Technical Centre) Battery Storage

Lathom (Pilkington Technical Centre) Battery Storage

Lathom (Pilkington Technical Centre) Battery Storage is an operational 2 MW battery storage site in West Lancashire, generating since 16 April 2019. Planning permission was granted on 31 August 2018, 4 months after submission. Operator of record: Lightsource BP.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 16 April 2019
Battery
Technology
Lightsource BP
West Lancashire
Authority
England

Planning and build timeline

Application submitted17 April 2018
Permission granted31 August 2018
4 months after submission
Operational16 April 2019
7 months after consent

Screening a site of your own?

RedlineUK · £39

West Lancashire approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lathom (Pilkington Technical Centre) Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Lancashire’s record on battery storage

West Lancashire has decided 5 battery storage schemes and approved 100%, taking a median of 4.5 months. See every battery storage scheme decision in West Lancashire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.50 km
Battery · Under Construction
49.91.4 km
Solar Photovoltaics · Operational
0.51.9 km
Landfill Gas · Operational
4.56.9 km
Landfill Gas · Operational
2.97.3 km
Landfill Gas · Operational
1.47.3 km
Wind Onshore · Operational
2.37.8 km
Wind Onshore · Operational
18.6 km

How big is Lathom (Pilkington Technical Centre) Battery Storage?

Lathom (Pilkington Technical Centre) Battery Storage has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lathom (Pilkington Technical Centre) Battery Storage?

REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lathom (Pilkington Technical Centre) Battery Storage approved and built?

The application was submitted on 17 April 2018. Permission was granted on 31 August 2018, 4 months later. The site became operational on 16 April 2019, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7037.